Concrete slab or wood joist: two different realities
In a wood floor, the drain runs between two joists, inside a single bay. Moving it from one side of that bay to the other is usually simple; crossing several load-bearing joists is a different matter, one that can call for reinforcing the structure.
A concrete floor needs a site-specific assessment before a drain is moved. Do not assume that a slab can be cut: the proposed route, structural effects and required approvals must be checked first.
| Floor type | What's generally possible | What complicates a move |
|---|---|---|
| Wood joist | Moving within the same joist bay, often without touching the structure | Crossing several load-bearing joists |
| Concrete slab (tower, converted industrial building) | Feasibility depends on the proposed route and structural assessment | Structural requirements, approvals and restoration work |
Slope and venting limit the distance
A drain needs to keep a constant slope toward the main stack; the farther it moves from that stack, the lower it has to drop, and the space under the floor isn't infinite. A sink, with its smaller drain, generally tolerates more distance than a toilet.
The vent needs to stay within a reasonable distance of the fixture so the drain flows properly instead of siphoning the water out of the trap. A plumber works that distance out before confirming a move, not after the floor has already been opened.
Condos add their own rules
A shared slab or common stack can involve both structural requirements and condominium authorization. Montréal lists engineer-signed structural plans where work affects the structure. Check the borough’s requirements and the syndicate’s approval before work starts. See Montréal’s renovation guidance.